Pedestrian Crossing Safety Enhancement RFP

Request for Proposals/Bids

City of Wood Village Pedestrian Crossing Safety Enhancement Solar RRFB Pedestrian Crossings on Northeast Halsey Street
From 244th Ave to Wood Village Boulevard
Bids Due: August 11, 2022 by 11 a.m.

Bid Package: Pedestrian Crossing Safety Enhancement

 The City of Wood Village is accepting bids until 11 a.m. on Thursday, August 11, 2022, for the installation of three rectangular rapid flashing beacon (RRFB) street crossings. Work shall include all procurement, demolition, construction, and striping described in the project plans and specifications. Assembly and installation of beacons must be performed according to manufacturer and engineer standards by a qualified electrician. Additionally, temporary traffic control and stormwater control will be required. Please see the construction documents for further details and submission requirements.

Bid Opening August 11, 2022
Award of Contract August 29, 2022
Notice to Proceed August 29, 2022
Completion November 15, 2022

Bid Documents:

Halsey Crossing Map

Project Manager:

Kyler Roberts
24200 NE Halsey Street
Wood Village, OR 97060
Phone (503) 489-6862
Email Kyler